Risk Assessment in Bridge Construction Projects Using Fault Tree and Event Tree Analysis Methods Based on Fuzzy Logic

Author:

Abdollahzadeh Gholamreza1,Rastgoo Sima2

Affiliation:

1. Associate Professor Faculty of Civil Engineering, Babol University of Technology, Babol 47148-71167, Iran e-mail:

2. Department of Civil Engineering, Tabari University of Babol, Babol 47148-71167, Iran e-mail:

Abstract

In this paper, interruption risk in construction activities of bridge projects is assessed in order to identify the main causes of its occurrence and also to determine the potential outcomes resulted from the risk occurrence. To do this, fault tree and event tree analysis (ETA) methods are applied. As the application of the traditional approach of these two methods is difficult in many cases due to limited access to information, fuzzy arithmetic can be considered as a useful tool. In this research, first, fault tree structure is created according to consequences resulted from the Delphi method. Then, the probability of risk occurrence is calculated by applying fault tree analysis (FTA) based on fuzzy logic. By establishing the structure of fault tree related to the failure risk of mitigation strategies, the main causes relating to failure of strategies are identified. The structure of the event tree is created using the obtained results; moreover, the expected monetary value (EMV) of risk event is computed. Finally, to validate the results obtained, a model is created by Monte Carlo simulation and then the results obtained by applying the two methods are compared. The EMV of the risk event evaluated in this paper is determined to be 9.93% of the project baseline cost.

Publisher

ASME International

Subject

Mechanical Engineering,Safety Research,Safety, Risk, Reliability and Quality

Reference26 articles.

1. Gereie, A., Taiiebat, M., Shakhs-Niaei, M., and Rezaei, K., 2007, “Providing a Model to Consider the Dependency of Uncertainties in Monte Carlo Simulation to Improve the Quantitative Analysis Process of Project Risk,” 3rd International Conference of Project Management, Aryana Industrial & Research Group, Tehran, Iran (in Persian).

2. Fuzzy Sets,1965

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3