Mitigating Making-Do Practices Using the Last Planner System and BIM: A System Dynamic Analysis

Author:

Karaz Mahmoud1,Teixeira José Manuel Cardoso1,Amaral Tatiana Gondim do2ORCID

Affiliation:

1. The Centre for Territory, Environment and Construction (CTAC), Department of Civil Engineering, School of Engineering, University of Minho, 4800-058 Guimarães, Portugal

2. Environmental and Civil Engineering Department, Federal University of Goiás, Goiânia 74605-220, Brazil

Abstract

Effective waste elimination is critical for the success of construction projects. Although several studies have focused on various aspects of construction waste, limited efforts have yet to investigate the dynamic effect of Making-Do (MD) practices on productivity, rework, defects, and material waste. From a lean construction perspective, this study aims to address MD waste using the Last Planner System (LPS) and BIM. First, the causal structure that can cause MD in construction projects was expressed in a causal loop diagram (CLD), and thematic analysis uncovered the strategies of LPS-BIM to eliminate MD identified by reviewing the literature. Secondly, twenty-five strategies from the LPS and BIM strategies to address MD using structural equation modeling (SEM) were assessed. Subsequently, a system dynamics model (SDM) for investigating LPS-BIM strategies on MD decisions in a construction project was formulated based on the underlying causal loop diagrams and the mathematical relations among the variables. Finally, the model was applied to three projects, and simulations for four LPS-BIM scenarios were carried out. The findings show that dynamic interactions among diverse production planning and control factors are critical in evaluating MD impacts on a construction project. The results demonstrate that the LPS-BIM approach resulted in an average 43.8% reduction in the tasks performed with MD, 45.3% of constraints, 66.5% of construction waste, an increasing 13.7% completion rate, and a 29.3% cost reduction, demonstrating that LPS-BIM is a more efficient solution for MD mitigation and construction planning. This study aims to guide construction planners and policymakers to better manage their production constraints by eliminating negative MD practices from their plans.

Funder

Fundação para a Ciência e a Tecnologia

Universidade do Minho

Publisher

MDPI AG

同舟云学术

1.学者识别学者识别

2.学术分析学术分析

3.人才评估人才评估

"同舟云学术"是以全球学者为主线,采集、加工和组织学术论文而形成的新型学术文献查询和分析系统,可以对全球学者进行文献检索和人才价值评估。用户可以通过关注某些学科领域的顶尖人物而持续追踪该领域的学科进展和研究前沿。经过近期的数据扩容,当前同舟云学术共收录了国内外主流学术期刊6万余种,收集的期刊论文及会议论文总量共计约1.5亿篇,并以每天添加12000余篇中外论文的速度递增。我们也可以为用户提供个性化、定制化的学者数据。欢迎来电咨询!咨询电话:010-8811{复制后删除}0370

www.globalauthorid.com

TOP

Copyright © 2019-2024 北京同舟云网络信息技术有限公司
京公网安备11010802033243号  京ICP备18003416号-3